GB/T 30026-2013 Crane Steel Welding Parameters and Quality Grades

GB/T 30026-2013 "Cranes — Welding of Steel Structures" is the dedicated standard governing welding procedures and weld quality for crane steel structures. Building on GB/T 30025 (Steel Structure Manufacturing), it details all welding-related technical requirements, including welding procedure qualification records (WPQR), welding consumable selection, welded joint design, welding process control, and weld quality acceptance.

As the specialized standard for crane steel structure welding, GB/T 30026-2013 systematically defines the full chain of technical requirements — from welding procedure qualification to weld quality acceptance. Correctly interpreting and implementing this standard is essential to ensuring weld quality in crane steel structures and guaranteeing safe operation of the equipment. This article provides a detailed breakdown of the standard's core content, helping welding engineers and technicians master process parameter selection and acceptance criteria.

GB/T 30026-2013 crane steel structure welding standard


Standard Positioning and Welding System

GB/T 30026-2013 is the dedicated standard for crane steel structure welding. Together with GB/T 30025-2013 (Steel Structure Manufacturing) and GB/T 30027-2013 (Steel Structure Processing and Inspection), it forms the three-part manufacturing standard system for crane steel structures. In relation to the general welding standard GB/T 50661-2011 (Code for Welding of Steel Structures) and NB/T 47014 (Welding Procedure Qualification for Pressure Equipment), this standard takes precedence for crane steel structure welding, while general requirements not specified herein are implemented per GB/T 50661. The standard classifies weld seams in crane steel structures into three levels based on criticality: Level 1 welds — joints that directly affect safety, such as main girder butt welds, T-joints between flange plates and web plates, and hook beam welds; Level 2 welds — primary load-carrying joints, such as fillet welds connecting stiffening plates to web plates and end carriage connection welds; and Level 3 welds — general structural welds.

Welding Consumable Selection

The standard specifies that welding consumables (electrodes, wires, fluxes, and shielding gases) shall be selected on the principle of equal-strength or under-matching strength:

Shielded Metal Arc Welding (SMAW) — For Q235B (≈S235JR) steel, use E43-series electrodes (e.g., E4303, E4315); for Q355B (≈S355JR) steel, use E50-series electrodes (e.g., E5003, E5015). Basic (low-hydrogen) electrodes such as E5015 must be dried before use per the manufacturer's manual (350–400°C for 1 h) and then kept in a portable heated electrode oven for immediate use. Rutile (acidic) electrodes such as E4303 shall be dried at 150°C for 1 h. Electrodes exposed to ambient air for more than 4 h must be re-dried (no more than two re-drying cycles).

Submerged Arc Welding (SAW) — Q235B is welded with H08A wire + HJ431 flux; Q355B with H08MnA wire + HJ431 flux. Flux must be dried before use (250–300°C for 2 h). Wire shall be free from corrosion and oil contamination.

Gas-Shielded Welding — For CO₂ gas-shielded welding, use ER50-6 wire (Φ1.0–1.6 mm) with CO₂ gas purity of no less than 99.5%. Mixed-gas shielded welding (80% Ar + 20% CO₂) is applicable to critical welds, reducing spatter and improving bead profile. Shielding gas flow rate shall be 15–25 L/min; when wind speed exceeds 2 m/s, windbreaks must be provided.

Level 1 Welds
Main girder butt / flange T-joint
100% UT + 10% RT
Level 2 Welds
Stiffening plate / end carriage
100% UT
Level 3 Welds
General structural components
Visual + MT sampling
Electrode Drying
Basic: 350–400°C
Rutile: 150°C
Preheating Temperature
Plate thickness ≥ 40 mm
Preheat ≥ 100°C
Post-Weld Heat Treatment
Plate thickness ≥ 60 mm
Stress-relief annealing

Welded Joint Design and Groove Types

The standard sets out clear requirements for the design of typical welded joints in crane steel structures:

Butt Joints — Splice butt welds in main girder flange plates and web plates shall be designed as full-strength butt welds, with groove type selected based on plate thickness: I-groove for plate thickness ≤ 8 mm (root gap 1–3 mm); V-groove for 8–20 mm (groove angle 60° ± 5°, root face 1–2 mm); X-groove for 20–40 mm (double-sided welding to minimize deformation); U-groove for plate thickness > 40 mm (to ensure full root penetration). Reinforcement of butt welds shall be controlled within 0–3 mm; excessive reinforcement must be ground flush.

T-Joints — The T-joint between the main girder web plate and flange plate is one of the most critical welds in overhead and gantry cranes. For main girders with Work Duty of A5 and Above, deep-penetration fillet welds or grooved fillet welds shall be used, with leg length no less than 0.7 times the web plate thickness. When web plate thickness is ≥ 12 mm, a single-sided or double-sided groove (groove depth ≥ 4 mm) shall be prepared to ensure full root penetration. The effective throat thickness of T-joints shall not be less than the design value.

Corner Joints and Lap Joints — For fillet welds connecting stiffening plates to web plates, the leg length shall be 0.5–0.7 times the web plate thickness (minimum 4 mm). The overlap length of lap joints shall be no less than 5 times the thickness of the thinner plate. Fillet weld ends shall be wrapped around the corner (wrap-around welding), with a wrap length no less than 2 times the leg length.

Welding Process Control

The standard imposes quantitative requirements for controlling key parameters during the welding process:

Preheating and Interpass Temperature — Preheating is mandatory when the base metal thickness is ≥40 mm or when the ambient temperature falls below 0°C. Recommended preheating temperatures: Q235B (≈S235JR) at 80–120°C, Q355B (≈S355JR) at 100–150°C, and Q420 at 120–180°C. The interpass temperature — measured on the base metal between adjacent weld passes — must not drop below the preheating temperature and must not exceed 230°C. Preheating coverage extends 100 mm on each side of the weld seam. Temperature verification is performed with a surface thermometer (infrared or contact type) at a distance of 50 mm from the weld.

Welding Heat Input — Heat input is calculated as Q = U·I/v, where U is voltage (V), I is current (A), and v is welding speed (cm/min). Insufficient heat input can produce hardened microstructures, increasing the risk of cold cracking, while excessive heat input degrades weld toughness. Recommended heat input ranges for common processes: Submerged Arc Welding at 20–45 kJ/cm, CO₂ gas-shielded welding at 10–25 kJ/cm, and shielded metal arc welding at 10–20 kJ/cm. Final values are established through the Welding Procedure Qualification Record (WPQR).

Welding Sequence — The main girder welding sequence is designed to minimize welding distortion: first weld the fillet welds between the web plate and the bottom flange plate (inducing the desired pre-camber), then weld the fillet welds between the web and the top flange plate, and finally weld the internal stiffening plates. Use backstep welding (with segments of 300–500 mm) or skip welding to distribute heat input evenly. For box girders, the four longitudinal fillet welds must be executed symmetrically by two welders working in tandem.

Post-Weld Hydrogen Release Treatment — For high-strength steel welds with plate thickness ≥60 mm, a post-weld hydrogen release treatment (holding at 200–250°C for 2–4 hours followed by slow cooling) must be applied immediately after welding to prevent cold cracking.

steel grade welding electrode Arc Welding Submerged Arc Welding CO₂Gas Shielded Welding Preheating Temperature(Plate Thickness≥40mm)
Q235B (≈S235JR) E4303/E4315 H08A+HJ431 ER50-6 80~120°C
Q355B (≈S355JR) E5003/E5015 H08MnA+HJ431 ER50-6 100~150°C
Q420B E5515-G H10Mn2+HJ431 ER55-G 120~180°C
Q460C E6015-G H08MnMoA+HJ350 ER60-G 150~200°C

Weld Quality Acceptance and Defect Assessment

This standard defines the acceptance grades and defect assessment criteria for weld quality:

Visual Inspection — All welds must undergo 100% visual inspection. Acceptance criteria: the weld surface must be free of cracks, lack of fusion, weld buildup, and undercut (undercut depth ≤0.3mm for Grade I welds, ≤0.5mm for Grade II, and ≤0.8mm for Grade III). No surface porosity is permitted on Grade I and Grade II welds; Grade III welds may have no more than 3 pores per 100mm of weld length, each with a diameter ≤1.5mm. Overall weld dimensions must be within ±2mm of the design dimensions.

Non-Destructive Testing — Grade I welds require 100% Ultrasonic Testing (UT) plus 10% Radiographic Testing (RT) as verification; Grade II welds require 100% UT; Grade III welds require visual inspection only. UT acceptance is assessed per GB/T 11345: Grade I welds must meet Grade II acceptance (no linear defects), and Grade II welds must also meet Grade II acceptance. RT acceptance is assessed per GB/T 3323: Grade I welds must meet Grade II acceptance, and Grade II welds must meet Grade III acceptance.

Mechanical Properties — Performance requirements for Welding Procedure Qualification Record (WPQR) test plates: tensile strength must not fall below the lower specification bound (LSB) of the base metal's characteristic value; bending test (d=4a, 180°) must show no cracks; impact energy KV₂ (-20°C) must be no less than 27J (Grade I welds) or 20J (Grade II welds). Metallographic examination: no cracks, no lack of fusion, no slag inclusion, and porosity rate not exceeding 2%.

Defect Rework — Non-conforming welds may be reworked, but no more than twice at the same location. Before rework, the defect must be completely removed (by carbon arc gouging or grinding) and verified. After rework, the area must be re-tested by UT and a rework record documented. A second rework requires approval from the technical manager. Kelude Heavy Industry's Welding Workshop strictly implements this standard, maintaining a first-pass yield of welds above 96% for all Grade I welds.


Steel Structure Welding Parameter Comparison Table

The comparison table below outlines the core parameter configuration for steel structure welding, serving as a reference for equipment selection and operational use.

← Scroll left / right to view full table →
Welding Method Weld Seam Type welding consumablesrequirements Preheating Temperature(℃) Quality Grade
Submerged Arc Welding Butt Weld Welding Wire H08MnA+HJ431 ≥100(Q345) Ⅰ/ⅡGrade
CO₂Gas-Shielded Welding Fillet weld/Butt Joint ER50-6Welding Wire ≥80(Q345) ⅡGrade
Manual Arc Welding Positioning Welding/Repair Welding E5015/E4315welding electrode ≥100(Q345) Ⅱ/ⅢGrade
flux-cored wire Welding Fillet weld E501T-1 ≥80(Q345) ⅡGrade

Frequently Asked Questions

Q: What is the main difference between GB/T 30026-2013 and GB/T 50661-2011 in terms of welding requirements?
A: GB/T 50661-2011, *Code for Welding of Steel Structures*, is a general-purpose welding standard for building steel structures, whereas GB/T 30026-2013 is specifically developed for welding crane steel structures. The main differences are: 1) Crane main girders have specific camber requirements, so the welding sequence is designed to achieve the desired upward camber; 2) The Work Duty classification for crane weld seams is higher than that for building steel structures, and the effects of fatigue load must be considered; 3) The load-bearing characteristics of cranes result in a higher proportion of T-joints and fillet welds. Both standards are comparable in terms of stringency, but they differ in inspection scope and defect acceptance criteria. In the crane industry, GB/T 30026 should take precedence for steel structure welding.
Q: What is welding heat input and how is it controlled?
A: Welding heat input refers to the amount of heat delivered per unit length of the weld seam, calculated as Q=η·U·I/v (where η is the thermal efficiency: approximately 0.9 for Submerged Arc Welding, 0.8 for gas-shielded welding, and 0.75 for shielded metal arc welding with a welding electrode). Excessive heat input causes grain coarsening in the heat-affected zone and reduces Toughness, while insufficient heat input leads to rapid Cooling and the formation of hardened microstructures. To control it: once the welding method is selected, the welder adjusts the welding Current, arc Voltage, and welding speed to keep the heat input within the range established by the Welding procedure qualification. In practical operation, the welder monitors the Ammeter and Voltmeter readings along with the travel speed to maintain consistent control.
Q: When is preheating required for welding Q355B steel?
A: Per this standard and GB/T 50661, preheating is required for Q355B steel in the following cases: 1) Plate thickness ≥40mm — preheat to 100–150°C; 2) Plate thickness 30–38mm with ambient temperature below 0°C — preheat to 80–120°C; 3) Highly restrained joints (e.g., box girder corners, cruciform joints) — preheat to ≥80°C regardless of plate thickness. Preheating slows the cooling rate of the welded joint, preventing the formation of hard martensitic microstructures and hydrogen-induced cold cracking. The preheating temperature must be maintained until welding is complete, and the interpass temperature must not fall below the preheating temperature.
Q: Is the 10% radiographic testing (RT) re-inspection rate for Grade 1 weld seams a sampling check or does it cover all critical areas?
A: The 10% RT re-inspection rate specified by the standard is not simply a length-based sampling check. Instead, it must be applied to the most critical areas of the weld seam: 1) crossed welds; 2) weld start and stop points; 3) reworked areas after defect repair; and 4) areas with abnormal surface discoloration (which may indicate internal defects). If the 10% re-inspection reveals defects exceeding the acceptance criteria, the sampling rate should be doubled to 20%. If defects are still found, 100% RT inspection is required. In practice, it is recommended to increase the RT sampling rate to 20%–30% for T-joint butt joints in Grade 1 weld seams and for field-installed circumferential welds.

Related News

contact

contact us

phone:
+86 13903802779

mail:3915269@qq.com

Working hours: Monday to Friday

Wechat
Wechat
SHARE
TOP