EN 13001-3-5:2016 Steel Structure Design for Bridge Cranes

EN 13001-3-5:2016, "Crane Safety Standard — Design of Steel Structures for Bridge Cranes," is the standard within the EN 13001 series that governs the detailed design of crane steel structures. It specifies section classification (Classes 1–4), main girder-to-end carriage connections (welded or high-strength bolted), camber (S/1000), crane rail tolerances (+/-2mm), and fatigue FAT grades.


Schematic diagram


Technical Requirements for Crane Steel Structure Design

The camber of the main girder is set to S/1000, and deflection under rated load is limited to L/400 to L/500. Main girder-to-end carriage connections use high-strength bolts of M20 or larger with friction-type connection surfaces prepared by sandblasting to achieve a friction coefficient of at least 0.45, or alternatively, full penetration welding with UT Class I inspection. Crane rail tolerance is +/-2mm, with rail fixing spacing not exceeding 500mm. Fatigue verification follows FAT 100 for fillet welds and FAT 80 for cruciform joints, with Miner's cumulative damage D ≤ 1.0. Thermal expansion gaps are reserved for temperature-induced movement. Kelude applies EN 13001-3-5 to the structural design of bridge crane steel structures, ensuring safe and reliable performance.

Key Design Parameters and Connection Details

The main girder-to-end carriage connection is a critical point in the structural design of bridge crane steel structures. Bolted connection surfaces are sandblasted to guarantee a friction coefficient of at least 0.45. Welding with backing bars ensures full root penetration. Annual deflection of the camber is limited to S/3000. Trolley rail joints incorporate expansion gaps to accommodate thermal deformation. For long-span main girders, thermal expansion clearance must be considered and reserved during design.

Section Class
1–4
Camber
S/1000
Connection
Welded + High-Strength Bolts
Rail Tolerance
+/-2mm
Fatigue
FAT100/80
Expansion
Reserved Gap
Component Requirement
Main Girder Camber S/1000Deflection<=L/400~L/500
Connection High-Strength Bolt M20+Slip-critical/Welding UT IGrade
Crane Rail +/-2mm Fixing<=500mm
Fatigue FAT100(Fillet weld)/80(Cross Joint)

Inspection & Tolerance Verification

Factory dimensional checks and weld seam UT inspection are performed prior to shipment. After installation, camber and crane rail tolerance measurements are taken on-site. Annual camber re-verification ensures deflection remains within S/3000.

Inspection Content
Factory Dimension+Weld Seam UT
Post-installation Camber+Crane Rail Tolerance
Annual Inspection Camber Re-verification

FAQ

Q: What are the key EN 13001-3-5 requirements for overhead crane steel structures?

A: The camber of the main girder must be S/1000, and the deflection under rated load must not exceed L/400 to L/500. Connections use high-strength M20 bolts with friction-type joints or full-penetration welds meeting UT Class I. The trolley rail tolerance is ±2 mm, and thermal expansion gaps must be provided.

Q: How do I select the FAT class for fatigue verification?

A: The FAT class is selected based on weld details — fillet welds are rated at 100 MPa, while cruciform joints are rated at 80 MPa. Fatigue-sensitive areas such as weld connection points and stiffener ends must be checked. A Miner's cumulative damage value of D ≤ 1.0 is considered safe.

Q: What are the design requirements for main girder–end carriage connections?

A: Bolted connection surfaces must be sandblasted to achieve a friction coefficient of at least 0.45. Welds require backing bars to ensure full root penetration. Rail joints must include expansion gaps to accommodate thermal deformation. Kelude performs detailed steel structure design in accordance with the standard to ensure a safe and reliable structure.

Q: Which design standard does Kelude follow for overhead crane steel structures?

A: Kelude designs steel structures for overhead cranes exported to Europe in accordance with EN 13001-3-5:2016. This covers section classification, camber, connection design, rail tolerances, and fatigue verification — ensuring safe and reliable structures that meet CE certification requirements.

Related News

contact

contact us

phone:
+86 13903802779

mail:3915269@qq.com

Working hours: Monday to Friday

Wechat
Wechat
SHARE
TOP