Gantry Crane Installation: Main Girder Lifting & End Carriage

Complete Crane Hoisting: Main Girder Lifting, End Carriage Assembly, and High-Altitude Connection Safety Control. Full crane hoisting is the highest-risk and most technically demanding phase of any installation project.

Complete crane hoisting is the highest-risk and most technically demanding phase of any installation project. As the heaviest single component, the main girder's lifting plan directly determines both installation safety and project schedule. Based on field hoisting experience across dozens of overhead and gantry crane installations, Kelude has developed a comprehensive technical solution covering dual-crane main girder lifting, high-altitude end carriage assembly, and structural bolt torquing. All hoisting operations must comply with GB 5074 Code for Construction and Acceptance of Lifting Equipment Installation Engineering and JGJ 276 Safety Technical Specification for Building Construction Hoisting Engineering.

Pre-hoisting preparation work

Pre-Hoisting Preparation Checklist

Before hoisting begins, the following preparations must be completed:

  • Runway beam acceptance: Foundation acceptance passed and intermediate handover records submitted.
  • Factory hoisting opening: Lifting opening or access path reserved in the factory building, with clearance meeting main girder entry requirements (main girder width + 500 mm minimum margin on both sides).
  • Crane selection: Chosen crane must meet lifting capacity and lifting height requirements — the combined weight of main girder, lifting spreader, and rigging must not exceed 75% of the crane's rated lifting capacity.
  • Lifting plan approval: Plan reviewed and approved by the supervision engineer and general contractor; dedicated safety officer present on site.
  • Rigging inspection: Wire ropes and rigging pass visual inspection and remain within their valid service period.
  • Certified operation: Crane operator and riggers hold valid certifications for their roles.

Before lifting, mark the crane bridge wheel mounting positions on the runway beams to enable rapid positioning once the main girder is set in place.

Reference lifting parameters for typical main girder capacities:

Rated Lifting Capacity (t)Main Girder Weight (t)Recommended Hoisting MethodMin. Crane Capacity Required (t)
103.5 – 5.5Single-crane lift16
16/3.25.5 – 8.5Single-crane lift25
20/57.5 – 11.5Single-crane lift32
32/512 – 18Dual-crane lift2 × 25
50/1018 – 28Dual-crane lift2 × 40
75/2028 – 42Dual-crane lift2 × 65
100/2038 – 55Dual-crane lift2 × 80

Note: The above values are typical reference ranges. Actual parameters must be calculated based on the specific crane design, span, and site conditions.

Dual-Crane Main Girder Lifting Procedure

For main girders exceeding 15 t, dual-crane coordinated lifting is recommended. The two cranes are positioned at the designated lifting points on the main girder, with each crane's lifting points arranged symmetrically about the girder's center of gravity. The lifting capacity of each crane must cover no less than 60% of the main girder's weight. During the lifting process, the two cranes must maintain synchronized hoisting and travel speeds, with the speed difference controlled within 5%. A dedicated lifting commander coordinates the entire operation via walkie-talkie, ensuring both cranes maintain consistent speed and direction. Before lifting, a trial lift of 200–300 mm is performed to verify the stability of the rigging and the braking performance of both cranes.

High-Altitude End Carriage Assembly and Bolt Torquing

After the main girder is lifted to the installation position, the end carriages are hoisted separately and connected at height. The connection bolts must be tightened in a specific sequence — from the center of the connection joint outward, alternating left and right — to ensure uniform stress distribution across the joint. High-strength bolts must be tightened in two stages: initial tightening to 50% of the final torque, followed by final tightening to the specified torque value. After torquing, the bolt heads and nuts must be marked with a paint marker for inspection and acceptance. The crane rail gauge tolerance must be verified after assembly, with the deviation controlled within ±3 mm.

Safety Control Points for Crane Hoisting Operations

Key safety control points during the hoisting process include:

  • Hoisting command: A dedicated lifting commander directs the entire operation; all signals must be clear and unambiguous.
  • Safety zone: A warning zone is established directly below the lifting path, with no personnel permitted to stand or pass beneath the suspended load.
  • Wind speed limit: Hoisting operations must stop when wind speed exceeds 10.8 m/s (Level 6 on the Beaufort scale).
  • Night operations: Adequate lighting must be provided at the hoisting site and along the lifting path when working at night.
  • Emergency plan: An emergency response plan must be in place before hoisting begins, covering scenarios such as crane failure, wire rope damage, and sudden weather changes.

Frequently Asked Questions (FAQ)

Q: How do two cranes coordinate synchronization during dual-crane lifting?
A: During dual-crane lifting, a lifting supervisor should be stationed at each end of the main girder, maintaining real-time communication with both crane operators via two-way radios. Kelude Heavy Industry standardizes the use of hand signals (ISO 4301) in its hoisting operations, with lifting speeds controlled between 0.1 and 0.15 m/s. After the main girder is lifted 200 mm off the ground, a 5-minute pause is taken to observe synchronization. During the actual hoisting process, the height difference between the two cranes must be kept within 100 mm.
Q: What should be done if the main girder deviates excessively from the crane rail centerline after positioning?
A: If the lateral deviation exceeds 2 mm after the main girder is set in place, thin steel shims should be inserted between the rail top surface and the wheel flange to correct the alignment. During adjustment, slightly lift the main girder (5–10 mm above the rail surface), insert the shims, and then lower it slowly for re-measurement. Never use pry bars to force the wheels against the rail, as this can damage the wheel tread surface and the rail top.
Q: What inspections are required for high-strength bolt assemblies upon delivery?
A: Upon delivery, high-strength bolt assemblies must be verified against the Factory Certificate and the Torque coefficient Test Report (for the same batch and specification). On-site re-inspection is required for bolt wedge load, nut proof load, and washer hardness (8 samples per batch for each). The average torque coefficient must fall within 0.110–0.150, with a standard deviation ≤ 0.010. Assemblies that do not meet these requirements must not be used.
Q: Which departments need to approve the Lifting Plan?
A: Once the hoisting plan is finalized, it must be reviewed by the technical director of the installation contractor, approved by the technical director of the general contractor, and signed off by the chief supervision engineer of the supervising firm. For high-risk lifting operations that exceed a certain scale—such as main girders weighing more than 40 t or spans exceeding 30 m—an expert review panel must also be convened.

Related News

contact

contact us

phone:
+86 13903802779

mail:3915269@qq.com

Working hours: Monday to Friday

Wechat
Wechat
SHARE
TOP